Phase-1 Power Grid Construction for Offshore Wind Connection

In order to meet Government's offshore wind power generation capacity target and large potential for offshore wind power connection in Taoyuan and Changhua area. TPC have planned the project named Phase-1 Power Grid Construction for Offshore Wind Connection, which provides grid connection capacity as 7.64GW(Changhua 6.5GW, Taoyuan 1.14GW). Construction period of the project are 8 years (January 2018 to December 2025)